ICE node Erfurt

Expansion of the ICE node Erfurt, drainage and underground cabling, engineering, rail construction and track laying, superstructure construction, installation of a signalling and passenger information system.

ICE-Knoten Erfurt

Client

DB Netz AG

Project volume

EUR 60.6 million

Construction time

2011-2018

Much of the work is being carried out without disrupting normal operations during the shutdown periods. The building partners are also coordinating the equipment companies, all planning services as well as run-out and test runs. Wittfeld is planning and managing the complex site logistics.